Montage Gold reports on its Q3-2026 activities

Montage Gold reports on its Q3-2026 activities Montage Gold reports on its Q3-2026 activities Koné mine first gold achieved • Plant already operating above nameplate • Strong exploration focus across the portfolio GlobeNewswire November 11, 2026
KONÉ OPERATIONAL ACTIVITIES
 • First gold pour achieved through the oxide circuit on September 26, 2026, and ahead of the initial schedule of Q2-2027
 • Process plant already operating at an average of over 90% of its 11 Mtpa nameplate capacity during October, with 104% of nameplate achieved during the last week of the month
 • Rapid progress achieved across the operation, with +15.2 million construction hours worked to date; +2,800 employees and contractors on site
 • Hard-rock comminution circuit construction remains on track for completion in Q2-2027, with significant progress made across civils, structural, mechanical and piping workstreams
 • Construction of the Koné mine remains on budget with $796.4 million of capital committed as at today, representing approximately 90% of the total upfront capital expenditure, with costs in line with expectations
 
EXPLORATION ACTIVITIES
 • Koné mine: 122,570 metres drilled during YTD-2026, out of the 130,000-metre full year program, where results provide increased confidence in the potential to continue expanding resources
 • Didievi project: 57,143 metres drilled during YTD-2026, out of the 85,000-metre full year program, resulting in further high-grade intercepts, with the drill program expected to yield an updated resource estimate
 • Wendé property: 8,982 metres drilled during YTD-2026, completing the 9,000-metre full year program, where recently published drill results increase confidence to delineate a maiden resource following upcoming drill programs
 • Mauritania: Exploration is well underway to inform target definition ahead of reconnaissance drilling across the Company’s Sfariat and Zednes exploration blocks, which cover an area of approximately 2,702 km2
 
FINANCIAL POSITION
 • Liquidity and Koné mine funding sources remain strong at $205.6 million compared to total remaining capital disbursements of $159.8 million, in addition to the Company’s cash flow generation potential from the oxide circuit


VANCOUVER, British Columbia, Nov. 11, 2026 (GLOBE NEWSWIRE) -- Montage Gold Corp. (“Montage” or the “Company”) (TSX: MAU, OTCQX: MAUTF) is pleased to report on its Q3-2026 activities, with highlights provided in Table 1 below.

Table 1: Business and financial highlights
 
 THREE MONTHS ENDEDNINE MONTHS ENDED 
All amounts in millions of USD, unless otherwise specifiedSept 30,
2026
Jun 30,
2026
Sept 30,
2025
Sept 30,
2026
Sept 30,
2025
Δ Q3-2026
vs. Q2-2026
OPERATIONAL HIGHLIGHTS      
Gold ounces produced, oz1,284 – – 1,284 – 1,284 
Gold ounces sold, oz– – – – – – 
CONSTRUCTION ACTIVITIES      
Cumulative hours worked, million hrs 14.4 12.0 4.8 14.4 4.8 +2.4 
Lost-Time Injuries Frequency Rate10.07 0.08 0.20 0.07 0.20 (0.01)
Total cumulative capital committed, inclusive of disbursed 753.6   686.0   428.0   753.6   428.0  +67.6 
EXPLORATION ACTIVITIES      
Metres drilled261,819 58,200 2,504 167,273 85,784 +3,619 
Exploration expenditure1,2 13.1   9.7   2.4   30.2   15.8  +3.5 
CASH FLOW AND LIQUIDITY POSITION1      
Cash flows used in investing activities (137.3) (128.0) (92.1) (375.7) (237.2)(9.3)
Cash flows generated from financing activities 105.3   212.8   156.8   318.0   307.7  (107.5)
Cash and cash equivalents, end of period 106.6   154.4   159.0   106.6   159.0  (47.7)
Total available liquidity 205.6   309.0   712.8   205.6   712.8  (103.4)
1As referenced in the Company’s Financial Statements and Management’s Discussion and Analysis for the three and nine months ended September 30, 2026, available on SEDAR+ and on the Company’s website.
2Excludes drilling done by African Gold prior to the April 29, 2026, transaction close.


The Company’s Condensed Interim Consolidated Financial Statements and associated Management’s Discussion and Analysis for the three and nine months ended September 30, 2026, have been filed under the Company’s profile on SEDAR+ (www.sedarplus.ca) and are available for download on the Company’s website.

Martino De Ciccio, Chief Executive Officer of Montage, commented: “This has been a quarter of transformation for Montage, with first production at our flagship Koné mine marking a key milestone in our journey to creating a premier, multi-asset African gold producer. We are pleased to have poured first gold on budget and well ahead of the initial schedule of Q2-2027.

The ramp-up of the oxide circuit is progressing well, with the plant already operating above nameplate capacity, and we remain well on track to declare commercial production this quarter. With potential cash flow generation from the oxide circuit now complementing our strong liquidity position, we look forward to completing the hard-rock comminution circuit, which remains on track for completion in Q2-2027.

We are also maintaining our focus on unlocking exploration value across our portfolio. At Koné, our exploration success continues to identify resource growth potential at higher-grade satellite deposits, with the objective of enhancing the production profile. At Didievi, recent high-grade drill results provide further excitement as we progress our next development asset. At the Wendé advanced greenfield exploration property, recent results provide strong confidence in our ability to delineate a maiden resource, with drilling ongoing, while in Mauritania, we have staffed a team following the award of permits earlier this year and exploration activities are now ramping up.

We are pleased with the momentum that we continue to generate across our business and we look forward to continuing to unlock value for all our stakeholders.”

ACTIVITIES OVERVIEW

Koné operations

First gold was achieved through the oxide circuit at the Company’s flagship Koné mine, in Côte d’Ivoire, on September 26, 2026, ahead of the initial schedule of Q2-2027. Rapid construction progress continues to be made across the operation, with 2.4 million construction hours worked in Q3-2026, and total hours worked now totalling over 15.2 million since construction commenced until today, alongside a Lost Time Injury Frequency Rate (“LTIFR”) of 0.07. Following the first gold pour, a total of approximately 888 kt were processed from the oxide circuit during October, with the plant operating at an average of over 90% of its 11 Mtpa nameplate capacity during the month, and with 104% of nameplate achieved during the last week of October. Mining activities are currently focused on the Koné deposit with mining at the higher-grade Gbongogo Main deposit expected to ramp up in late Q4-2026, while mining at other recently discovered higher grade satellite deposits is expected to commence over the course of 2027. The Company remains well on track to declare commercial production in Q4-2026. Significant progress is being made on all key components of the hard-rock circuit, with major concrete pours complete, and structural, mechanical and piping (“SMP”) workstreams progressing as expected across the primary and secondary crushers, screening areas and high-pressure grinding rollers (“HPGR”) area. A total of $753.6 million of capital had been committed as at quarter-end (inclusive of $725.2 million disbursed), which has further increased to approximately $796.4 million as at today, representing approximately 90% of the total $885.0 million capital expenditure, with prices in line with expectations.

Exploration portfolio activities

The Company continues to be focused on unlocking value through its exploration programs across its multi-asset portfolio. As shown in Table 2 below, a total of 224,000 metres of drilling is underway for 2026 across the Koné, Didievi and Wendé properties, with further details by asset provided in the sections below. Exploration expenditure, including amounts related to non-drilling exploration activities, across all assets is expected to amount to $46 million for 2026, including $3.3 million spent by African Gold prior to the transaction close on April 29, 2026. During Q3-2026, a total of 61,819 metres were drilled across the assets, with exploration expenditure for Montage, amounting to $13.1 million. For the nine months ended September 30, 2026, a total of 188,695 metres were drilled across the assets amounting to an exploration expenditure of $33.5 million, with exploration expenditure for Montage amounting to $30.2 million for 167,273 metres, in addition to $3.3 million incurred by African Gold to complete 21,422 metres on Didievi prior to the close of the African Gold acquisition.

Table 2: Group exploration drilling program (pro forma post-African Gold transaction close)
 
 THREE MONTHS ENDEDNINE MONTHS ENDED2026 FULL YEAR
DRILL PROGRAM
 Sept 30, 2026Jun 30, 2026Sept 30, 2026
DRILLING METRES
(in metres)
    
Koné mine31,99443,322122,570130,000
Didievi project127,38213,15957,14385,000
Wendé properties2,4436,5398,9829,000
Mauritania––––
Other––––
Total61,81963,020188,695224,000
EXPLORATION EXPENDITURES
(in millions of USD)
    
Koné mine6.96.120.422
Didievi project14.62.79.917
Wendé properties0.21.01.22
Mauritania1.40.62.04
Other–––1
Total13.110.433.546
1Q2-2026 includes 8,339 metres drilled by Montage, amounting to $2.0 million, post the completion of the African Gold transaction on April 29, 2026, and 4,820 metres drilled prior to the transaction close , amounting to $0.7 million. Q1-2026 is comprised of 16,076 metres, amounting to $2.6 million drilled by African Gold.


KONÉ MINE, CÔTE D’IVOIRE

Operational overview

Oxide circuit completion and ramp-up

Table 3: Koné mine monthly operating performance indicators
 
Operating DataAug 2026Sep 2026Oct 2026
Mining   
Ore mined, kt4741,0172,333
Waste mined, kt91579814
Open pit strip ratio, waste:ore0.190.570.35
Processing   
Ore milled, ktn.a475888
    
    
    
    
Mill head grade, g/tn.a0.770.82
    
    
    
    
Recovery, %n.a9295
    
    
    
    
Gold Produced, ozn.a1,28423,462
    
    
    
    


Figure 1: Fully operational oxide circuit overview

Figure 1


Figure 2: Mining of the Koné deposit

Figure 2


Hard-rock comminution circuit

Figure 3: Hard-rock comminution circuit overview

Figure 3


Figure 4: Hard-rock comminution circuit stages

Figure 4

Koné exploration activities

DIDIEVI PROJECT, CÔTE D’IVOIRE

WENDÉ ADVANCED GREENFIELD EXPLORATION PROPERTY, CÔTE D’IVOIRE

MAURITANIA EXPLORATION PORTFOLIO

CASH FLOW, LIQUIDITY SOURCES AND CAPITAL REQUIREMENTS

Cash flows used in investing activities totalled $137.3 million in Q3-2026, a $9.3 million increase from $128.0 million in Q2-2026. This variance was primarily driven by the timing of cash outflows related to construction expenditures at the Koné mine, and $24.8 million cash consideration in relation to the transaction with the minority shareholders of the Didievi project. To fund the transaction, in Q3-2026 the Company has successfully closed and subsequently fully drawn the unsecured term loan of $75.0 million with Macquarie Bank Limited. Cash flows generated from financing activities in Q3-2026 was $105.3 million, representing a $107.5 million decrease from $212.8 million of cash flow generated from financing activities in Q2-2026, primarily driven by $125.0 million of loan facilities drawdown, offset by $19.8 million related to the acquisition of an additional 15.5% interest in Kouroufaba Gold. Q2-2026 included the $156.25 million Wheaton Stream drawdown and the $55.7 million AFG Loan drawdown.

As at September 30, 2026, the Company had a consolidated cash balance of $106.6 million, compared to $191.8 million as at December 31, 2025, a decrease of $85.2 million. This is primarily driven by the $180.7 million of loan facilities drawdown, and $156.3 million of Wheaton Stream drawdown, and $10.6 million proceeds from disposal of Aurum shares, offset by $368.3 million spent mainly on development and construction of Koné mine, $27.8 million spent on exploration and general administrative activities, and $44.5 million cash consideration paid in relation to the transaction with the minority shareholders of the Didievi project.

As at September 30, 2026, the Company had available liquidity of $205.6 million, comprised of the $75.0 million Wheaton Loan Facility, $106.6 million of cash on hand and $24.0 million of other liquid assets, in addition to the Company’s cash flow generation potential from the oxide circuit.

A total of $753.6 million of capital had been committed for construction of the Koné mine as at September 30, 2026 (inclusive of amounts disbursed), which further increased to $796.4 million, representing 90% of the total $885.0 million capital expenditure estimate, with costs in line with expectations. As at September 30, 2026, a total of $725.2 million has been disbursed for construction of the Koné mine, of which $101.4 million in Q3-2026, with approximately $159.8 million remaining to be disbursed to completion of the hard-rock comminution circuit (inclusive of contingencies).

UPCOMING CATALYSTS

Key upcoming catalysts by asset across the Company include:

Table 4: Key upcoming catalysts by asset
 
PROPERTYCATALYST
Koné mine
  • Further exploration results from the ongoing 130,000-metre drilling program
  • Updated life of mine plan along with 2026 year-end reserves and resources in late Q1-2027
  • Ramp-up to commercial production on the oxide circuit in Q4-2026
  • Completion of the hard-rock comminution circuit in Q2-2027
Didievi project
  • Exploration results from the ongoing drilling program, expected to yield an updated resource estimate
Wendé property
  • Further exploration results from the 9,000-metre drill program in Q4-2026
Mauritania greenfield properties
  • Early-stage exploration activities ongoing with scout drilling to commence in Q1-2027


ABOUT MONTAGE GOLD

Montage Gold Corp. (TSX:MAU) is a Canadian-listed company focused on creating a premier multi-asset African gold producer, with its flagship Koné mine, located in Côte d’Ivoire, at the forefront. Based on the Updated Feasibility Study published in 2024 (the “UFS”), the Koné project has an estimated 16-year mine life and sizeable annual production of +300koz of gold over the first 8 years and entered production in Q3-2026. The Company has also built a high-quality, multi-asset growth pipeline including the Didievi and Wendé properties in Côte d’Ivoire, and a portfolio of prospective exploration tenements in Mauritania.

QUALIFIED PERSONS STATEMENT
The scientific and technical contents of this press release have been verified and approved by Mr. Peder Olsen, a Qualified Person pursuant to NI 43-101. Mr. Olsen, President and Chief Development Officer of Montage, is a registered Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM).

CONTACT INFORMATION

For Investor Relations Inquiries:
Jake Cain
Strategy & Investor Relations Manager
jcain@montagegold.com
+44-7788-687-567
For Media Inquiries:
John Vincic
Oakstrom Advisors
john@oakstrom.com
+1-647-402-6375
For Regulatory Inquiries:
Kathy Love
Corporate Secretary
klove@montagegold.com
+1-604-512-2959


FORWARD-LOOKING STATEMENTS
This press release contains certain forward-looking information and forward-looking statements within the meaning of Canadian securities legislation (collectively, “Forward-looking Statements”). All statements, other than statements of historical fact, constitute Forward-looking Statements. Words such as “will”, “intends”, “proposed”, “expects”, “anticipates”, “plans”, “on track”, “potential” or similar expressions are intended to identify Forward-looking Statements. Forward-looking Statements in this press release include statements related to the Company’s objectives of achieving commercial production on the oxide circuit in Q4-2026, and remaining on-schedule and on-budget for completion of the hard-rock comminution circuit in the second quarter of 2027; generating strong cash flows from the Koné mine; the sufficiency of the Company’s available liquidity, together with cash flow generation from the Koné mine; the continued ramp-up of throughput and recoveries of the oxide circuit; the ramp-up of mining at the Gbongogo Main deposit in late Q4-2026 and the commencement of mining at other higher-grade satellite deposits in 2027; the timing of major equipment and back-up power generator deliveries; the items listed under the heading “Upcoming Catalysts”; the Company’s mineral reserve and resource estimates; results of ongoing and planned exploration and drill programs, including results of grade control drilling programs; expected recoveries and grades of the Koné project; timing in respect of the commencement and completion of construction of various components of the Koné project, the length of construction and of the mining operations at the Koné project, including estimated construction costs; timing and amount of necessary financing related to the mining operations at the Koné project; the timing and amount of future production from the Koné project; anticipated mining and processing methods of the Koné project; anticipated mine life of the Koné project; anticipated operational efficiencies and flexibility and other benefits of the construction of the oxide circuit; the publication of updated mineral reserve and resource estimates and an updated LOM plan in 2027; the potential for the Didievi project to become the Company’s next development asset; and further information related to exploration and drill programs, exploration results, permitting activities, mineral resource estimates and timing thereof at the Didievi project, the Wendé property and Mauritania.

Forward-looking Statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that any Forward-looking Statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements, including that the returns from the Koné project will be lower than estimated, that additions to the mineral resources will not be achieved or that the remaining cost of construction of the Koné project will be higher than estimated, that the updated LOM plan will indicate lower financial returns or production, or that the acquisition of African Gold will not result in any benefits to Montage. Important factors that could cause actual results to differ materially from those anticipated include uncertainties inherent in the preparation of mineral reserve and resource estimates and definitive feasibility studies, and in delineating new mineral reserve and resource estimates, including but not limited to, assumptions underlying the production estimates not being realized, incorrect cost assumptions, decreases in the price of gold, unexpected variations in quantity of mineralized material, grade or recovery rates being lower than expected, unexpected adverse changes to geotechnical or hydrogeological considerations, or expectations in that regard not being met, unexpected failures of plant, equipment or processes (including construction equipment), delays in or increased costs for the delivery of construction equipment and services, unexpected changes to availability of power or the power rates, failure to maintain permits and licenses, higher than expected interest or tax rates, adverse changes in project parameters, unanticipated delays and costs of consulting and accommodating rights of local communities, environmental risks inherent in the Côte d’Ivoire, title risks, including failure to renew concessions, unanticipated commodity price and exchange rate fluctuations, delays in or failure to receive access agreements or amended permits, and other risk factors set forth in the Company’s Annual Information Form available at www.sedarplus.ca, under the heading “Risk Factors”. The Company undertakes no obligation to update or revise any Forward-looking Statements, whether as a result of new information, future events or otherwise, except as may be required by law. New factors emerge from time to time, and it is not possible for Montage to predict all of them, or assess the impact of each such factor or the extent to which any factor, or combination of factors, may cause results to differ materially from those contained in any Forward-looking Statement. Any Forward-looking Statements contained in this press release are expressly qualified in their entirety by this cautionary statement.

Photos accompanying this announcement are available at

https://www.globenewswire.com/NewsRoom/AttachmentNg/c9887100-2f21-4310-883d-b5a1710a0252

https://www.globenewswire.com/NewsRoom/AttachmentNg/a1708e54-8069-4252-90da-ddd95553e5a8

https://www.globenewswire.com/NewsRoom/AttachmentNg/2d06a203-17cd-45ce-9f95-e00c46407bb9

https://www.globenewswire.com/NewsRoom/AttachmentNg/6170919f-faaf-4e01-bf6a-15d2512a3393


Primary Logo